– Hastie Lane Box Culvert Construction Schedule as follows:
September 23-25, 2024 Multiscape to excavate and prep for Culvert Sections No.1, 2, 3, 4 and Downstream Headwall Sections(2). Build access road.
September 26, 2024 Old Castle deliver Culvert Sections No.1, 2, 3, 4 and Downstream Headwall Sections(2). Multiscape set Culvert Sections No.1, 2, 3, 4 and Downstream Headwall Sections. Backfill Culvert Sections and move access road. (Post Tension)
September 27, 2024 PP&L Power Outage. Old Castle deliver Culvert Sections No.5, 6, 7 and Upstream Headwall Sections. Multiscape set Culvert Sections No.5, 6, 7 and Upstream Headwall Sections. Backfill Culvert Sections restore road to normal traffic configuration. (Post Tension)
October 7 – 11, 2024 Roadway excavation, subbase, fine grade and bituminous
October 14, 2024 – Guide Rail Installation and Project walk through
– As of 04/29/2024, the bridge on Miller Road was shut down by Luzerne County. Luzerne County is the responsible party for the Miller Road Bridge and is currently having their engineers work to create a report. Any updates from the County will be posted here under Township News.